[Fixed] New Members Not Made Available for Assignment
Page: 1
Rafiki Cai
on Jul 9. 2006. 5:01 am
I've just installed AC. I initially added two members.
After adding a project, and beginning the task list. I decided
that I wanted to add another member. I did so.
Now that I want to assign a task to that new member, I find
that they are not visible in the 'Assign To' pull down menu.
----
Also, when I go back to edit a Task List (that I only left momentarily
to add a member), I see that a separate entry is made in the Recent Activity
area (for that edit). This seems excessive. Why not just let the single Task
List entry (for Recent Activity) suffice.
In Service of THE ONENESS,
Rafiki "The Digital Doctor" Cai
After adding a project, and beginning the task list. I decided
that I wanted to add another member. I did so.
Now that I want to assign a task to that new member, I find
that they are not visible in the 'Assign To' pull down menu.
----
Also, when I go back to edit a Task List (that I only left momentarily
to add a member), I see that a separate entry is made in the Recent Activity
area (for that edit). This seems excessive. Why not just let the single Task
List entry (for Recent Activity) suffice.
In Service of THE ONENESS,
Rafiki "The Digital Doctor" Cai
Topic is locked. If you have something important to say about issues discussed on this page please write at hi@a51dev.com.