I realize that there is no documentation for aAC but is there an overview about how the system works once you get it up and running.

I am not a Base Camp user and am not interested in their offering and can't find much there anyway.

So is there a how to that exists anywhere?
avatar
yerg on Feb 12. 2007. 7:00 am
I'm not one for answering my own posts but I'm going to today.

Can anyone explain how the Tasks /Milestones processes fit together.

I can't get any logic out of the process nor can my testers.
avatar
Ilija Studen on Feb 13. 2007. 4:35 pm
Milestone can have multiple task lists (and messages BTW), task list can have multiple task. For instance, milestone Beta launch can have two task lists:

1. Prepare product with following tasks:

- build product using build tool
- package version for Windows
- package version for Mac
- test if whole process is working on Windows
- test if whole process is working on Mac
...

2. Announce beta version with tasks:

- write and post announcement on company blog
- upload packages
- update download page
- update releases page
- update homepage to show the most recent version

Milestone <> Task list relation is optional to give more flexibility to the system.
activeCollab team member
avatar
pixelita on Jun 24. 2007. 8:45 pm
And a milestone can have many tasks under it. Milestones probably should be broader than tasks.

For example, for a web design project, you would probably have these milestones:
1. Design Concept/Creative Brief
2. Execute Design
3. Execute Layout and Backend
4. Local Testing
5. Deployment
6. Testing on Live Site
7. Project Closed

And within each, you would have several tasks and subtasks. At least that's how I'm using it currentlyl. :-)
avatar
psyclo on Jul 23. 2007. 4:26 pm
If the Milestones are "bigger" than TaskLists and Tasks, why aren't they right next to the Project Overview tab. It appears, by the tab order, that Milestones are "below" tasks, since they are to the right in tab order. Just a UI thing.
Topic is locked. If you have something important to say about issues discussed on this page please write at hi@a51dev.com.

RSS IconRecent posts in this topic