This topic is locked, no new messages can be posted
avatar gtcaz Dec 4. 2006. 12:40 pm
Is there currently any way to mark a task deferred, postponed, on-hold or something like that? Thanks!
avatar Ilija Studen Staff Dec 4. 2006. 12:41 pm
No, there is not. Only supported states are open and completed.

You can prefix tasks with "On-Hold: Task description ....".
avatar gtcaz Dec 4. 2006. 12:44 pm
OK. Thanks. Maybe an on-hold to-do list. (But no direct way to move tasks between lists, so maybe that's not the way to go.)
avatar gtcaz Dec 4. 2006. 12:44 pm
Perhaps that's on the way: http://www.activecollab.com/forums/topic/326/
avatar Ilija Studen Staff Dec 4. 2006. 12:45 pm
You can move tasks between lists. Click on edit task icon and select a new list from drop down box.
avatar gtcaz Dec 4. 2006. 12:47 pm
Oh, perfect. I'll just create a "Deferred" task list. Cheers!

Topic is locked

If you have something important to say about the issues discussed in this post please write at hi@a51dev.com.