Just been playing around rescheduling a milestone and noticed this just below the date selectors:

With successive milestones

This milestone does not have any successive milestones

Is this something that is in place, and if so how do you set the successive milestones? Or is this something for the future?

Thanks
Paul Dixon
avatar Pro
pdiki on Oct 17. 2007. 6:19 am
Ah found it, sorry.
Paul Dixon
avatar Pro
toby on Nov 13. 2007. 3:52 am
Is that feature part of the demo? I can't find a way to set successive milestones. Choosing 'all' on the rescheduling screen does not have any effect...
avatar Staff
Ilija Studen on Nov 13. 2007. 4:34 am
Successive milestones are milestones that are due after the due date of milestone you are rescheduling, there is no special way of defining them. This feature is available in the demo.
activeCollab Team Member
avatar Pro
toby on Nov 13. 2007. 5:02 am
Oh, I see. I though that you might be able to define, which milestones where successors to a particular milestone, sort of like dependencies.
avatar Staff
Ilija Studen on Nov 13. 2007. 5:04 am
activeCollab does not support milestone dependencies - just set the dates and you are good to go.
activeCollab Team Member
avatar Pro
toby on Nov 13. 2007. 5:05 am
Got it. Thank you.