Login or Register

RSS IconRecent posts in this topic

avatar
cyandesign on May 20. 2008. 7:15 pm
I have created a couple of taks on the main level page, for a project.

I don't have the pages viewable to the client, but they are still showing up as 2 tasks finished.

Does anybody know if there is just anyway to delete the tasks? I can't figure out how to do that.

Thanks.
Tom
avatar
Ilija Studen on May 21. 2008. 5:56 am
No, there is no way to hide this information. Project progress is based on number of completed task vs number of total tasks in the system and ignores visibility.
activeCollab team member
avatar
cyandesign on May 21. 2008. 7:12 am
Hi Ilija,

But is there anyway to delete any tasks from that page?
avatar
Ilija Studen on May 21. 2008. 7:15 am
If you wish to completely remove them move them to Trash and than empty Trash.
activeCollab team member
avatar
cyandesign on May 21. 2008. 12:13 pm
There are no options to move them to the trash.
avatar
Ilija Studen on May 21. 2008. 2:43 pm
Is there anything specific about these tasks? Where they create by another administrator or something like that? There should be a little trash Move to Trash icon next to every tasks as outlined in the screenshot.
activeCollab team member
avatar
cyandesign on May 21. 2008. 7:31 pm
Hi Ilija,

I did nothing weird at all. Here is what I did:

Created new Project.

Clicked on "Pages" Tab

Clicked on Side Tab "New Task"

I now have a task that I can not delete. See attached screenshot (there is not Delete "x").


avatar
Ilija Studen on May 22. 2008. 5:42 am
Ok, found it. This will be covered with the next build.
activeCollab team member
avatar
cyandesign on May 22. 2008. 5:46 am
Cool, you guys Rock!

RSS IconRecent posts in this topic